PJM Wants Power Plants and Large Loads Studied Together

PJM Wants Power Plants and Large Loads Studied Together A Nov. 16 FERC filing would study data centers and new generation in one annual cycle, with earlier deposits and interim service while grid upgrades are built. PJM Interconnection asked the Federal Energy

Illustrative imageIllustrative image

PJM Wants Power Plants and Large Loads Studied Together

A Nov. 16 FERC filing would study data centers and new generation in one annual cycle, with earlier deposits and interim service while grid upgrades are built.

PJM Interconnection asked the Federal Energy Regulatory Commission (FERC) on Nov. 16 to approve a process it calls Fast Energization. It would study new power plants and new large electricity users, such as data centers, together in one annual cycle. The grid operator says that would cut projected study times from two years to one. Nothing has been approved. PJM asked FERC for a 60-day comment period, which would put comments due around Jan. 15, and for a ruling within 120 days.

The filing answers a June 18 FERC order directing grid operators to justify or reform how they connect large loads. It also follows FERC's Oct. 9 decision rejecting PJM's earlier plan to curtail new large loads first in a shortage unless they brought their own new capacity. FERC kept a 50-megawatt definition of a large load and a registry of those customers, but found the curtailment and compensation terms reached into retail rates, which states regulate. Under that plan, an earlier connection would have depended on how much load a site could shed during a shortage.

What a Combined Study Would Change

Today a data center's request for transmission service and a generator's request to interconnect move on separate tracks. PJM's Nov. 5 presentation to members would place them in a single 12-month cluster and size grid upgrades for the whole group. Applicants would receive quick screening results with preliminary upgrade costs and build times before most of their money is committed. To stay in, a large load would need verified site control. It would also need evidence that its local transmission owner has approved the project to proceed.

PJM's slides show money committed in stages, with estimated amounts of $5,000 per megawatt at the first decision point, plus 35% of assigned reliability upgrade costs up to a cap, and $8,000 per megawatt at the second, when the full upgrade cost is on the line. For a 300-megawatt campus, the per-megawatt amounts alone would come to $1.5 million and then $2.4 million. The slides label these figures as estimates, and the filed tariff language may differ.

Projects that cannot get full firm service on day one would receive a year-by-year schedule of interim rights while upgrades are built. For large loads, that could be a fractional firm service or a non-firm service that can be cut back when local lines are constrained. A campus able to run on partial grid power at first, or one with generation of its own on site, could put that schedule to use sooner.

The Case PJM Is Making

When PJM's reformed interconnection process took applications this spring, 811 projects totaling 220 gigawatts applied, nearly half of that capacity gas-fired. "This is good news because we need all the generation we can get," David Mills, PJM's interim president and CEO, said at the time. A shared study is meant to tell a developer early whether both power and wires exist where it wants to build. PJM also says the process would give states "clear insight into the costs of serving data centers and other Large Load customers," which regulators can use when setting what those customers pay.

PJM also filed a companion proposal on reliability the same day, after nearly 3.9 gigawatts of data centers switched unexpectedly to on-site generators during a routine transmission disturbance on July 22, the largest such transfer in its history. The proposal would require computing loads of about 50 megawatts and up to stay connected through voltage and frequency disturbances, with an effective date of Jan. 16, 2027, if FERC agrees. PJM counts about 10 gigawatts of that load on its system now and expects up to 30 gigawatts more by 2030.

Why Corporate Buyers and Data Center Groups Object

In an Oct. 2 letter written before the filing, the Corporate Energy Buyers Association and the Data Center Coalition urged PJM's board to take a narrower path. FERC's order "does not require PJM to overhaul its entire generation interconnection queue," wrote John Miller, the buyers association's director of transmission policy, and Morgan Sipple, the coalition's director of energy policy. They warned that utility approval followed by an annual window and a PJM study "could mean nearly two years between Transmission Owner approval and completion of the PJM process."

The groups also warned that a generator paired with a load would wait on that load's cycle, and "the generator could be held out of the queue during that wait, delaying new supply that PJM urgently needs," they wrote. The two groups pointed to MISO and SPP, grid operators that plan for load and generation in parallel and coordinate between the tracks. They asked the board to pilot study automation inside PJM's existing cycle and said "PJM has not demonstrated that this proposal will deliver the speed, certainty, or transparency" it promises.

How the Trade-Off Looks to a Project Sponsor

For a company with a campus planned in PJM territory, the proposal trades earlier cost information for earlier financial commitments. On large projects, power and financing now hinge on each other, so an energization date shapes when capital moves. The proposal would swap an open-ended wait for a fixed calendar with two points to stay or leave. A project that screens well would know its upgrade exposure within months. One facing a large upgrade bill could withdraw at the first decision point with less money spent.

A fixed calendar cuts the other way for a project that misses a deadline, which then waits a full cycle. Construction of buildings and substations, along with any power agreement with a new generator in the same cluster, would have to line up with that window. Missing one deadline could push energization back a year.

What to Watch Before FERC Rules

FERC's notice will set the actual comment deadline, and comments from the groups that objected in October will show whether the filed version answered their concerns. The commission is separately weighing how PJM makes decisions. Before either question is settled, PJM's capacity auction for the 2029/2030 delivery year, scheduled for December, will show how much new supply is clearing in the region where these data centers want to connect.